Guide · Yard design · 09 of 14
Planning a backyard around artificial turf: patio, fire feature, outdoor kitchen and pergola, and the order the work goes in
Laying out turf, a patio, fire feature, outdoor kitchen and pergola in a Northern Colorado backyard: which parts need permits, and the order the trades go in.
Updated
Not legal advice
A patio, fire feature, outdoor kitchen and pergola need footings or buried lines, and usually an inspection. Turf needs neither, so it goes in last, once the rooms are settled on paper. Not legal advice where this page touches codes and covenants.
How do you divide a backyard into rooms around the turf?
Give each use the surface that suits it: anything hot or heavy on hardscape, the open ground you walk and play on in turf.
| Room | Surface underfoot | Why |
|---|---|---|
| Dining and lounge | Patio: pavers, flagstone or concrete | Furniture weight and spills |
| Outdoor kitchen | Patio, with the counter on its own base | Grease and heat; gas, power and water come up here |
| Fire feature | A noncombustible pad or the patio, turf stopping at its edge | Your fire district sets the distances |
| Shade | A pergola or patio cover over the seating | Afternoon sun on the seating |
| Open lawn and play | Turf | The space that used to take the water |
| Putting | A putting green | Shaping, cups and fringe: putting green design |
Then place the rooms:
- Patio against the house, turf beyond it. The 2021 International Residential Code wants the ground to fall at least 6 inches in the first 10 feet from a foundation, and hard surfaces within 10 feet to slope at least 2 percent away (IRC R401.3); ask your town which edition it enforces. The Colorado Geological Survey also flags poor drainage and watered plantings against foundations on expansive clay (CGS). A sloped patio at the back door answers both, and keeps turf back from window glare that can melt it.
- Shade the seating. Fort Collins averages 29.5 days a year at or above 90°F (NOAA’s 1991–2020 normals).
- Keep shoveled paths hard. Put pavers or concrete where you’ll shovel in winter, and turf where you won’t.
On a golf-course lot, The Masters at Mariana Butte in Loveland encourages trees and shrubs for golf-ball protection, names pergola-type structures as another option and will likely reject poles with netting (Deer Meadows guidelines), so one pergola can be both shade and ball stop.
In what order does everything go in?
From the ground up, turf last. Select Surfaces’ installation guide wants drainage, irrigation, electrical, water and gas changes made, and pavers, lighting and gardens in place, before turf work starts (Select Surfaces).
| Step | What happens | Why it goes here |
|---|---|---|
| 1. Plan and approvals | One scaled drawing; HOA or metro-district approval, then town permits | Committee approval isn’t a permit, and review takes weeks |
| 2. Locates and grading | Colorado 811 for public lines, a private locator for private ones; grades set to drain | Water must leave the house before anything is built on the grade |
| 3. Underground runs | Gas pipe, electrical conduit, irrigation and bed drip lines, spare sleeves | Inspected with trenches open; nothing trenched through turf later |
| 4. Footings | Piers for a pergola or patio cover, bases for the kitchen and fire feature | Dug to frost depth and inspected open |
| 5. Hardscape and structures | Patio, walls, kitchen, fire feature, pergola; final inspections | Turf is cut to finished hardscape, not the reverse |
| 6. Planted beds | Planting, then a drip test | Leaks show before turf hides the lines |
| 7. Turf | Base, turf, seams, infill, edges | The last trade on the ground |
| 8. Finishing | Light fixtures, furniture, grill | Carried across the patio, not dragged over the lawn |
- Private lines. Colorado 811 doesn’t mark private lines such as gas lines to backyard grills (Colorado 811), so keep an as-built drawing of every line you add, with its depth.
- Lines under the lawn. Integriturf’s installation guide runs planter water and power below the subgrade and suggests spare conduit sleeves for future access (Integriturf). Cap the sprinkler zones the turf retires.
Which parts need a town permit?
Mostly the structures, gas and wiring, as read in September 2026; the turf’s own rules are on each town’s page.
- Fort Collins. A pergola or patio cover needs a permit if it is attached to the house, taller than 8 feet, over 120 square feet or within 3 feet of a lot line (pergola guide, patio cover guide), and exempt work still has to meet code. New outlets and light fixtures need an electrical permit, and a job mixing trades files as one remodel/alteration permit (Building Permits); ask Building Services how that applies to an outdoor kitchen. Built-in wood-burning fire pits aren’t allowed; a gas one needs a permit and a piping inspection, installed by the homeowner or a licensed plumber or HVAC contractor (Fire Pit Policy). A permitted project adding more than 350 square feet of hard surface, such as a patio roof, must include drainage information (Fort Collins Utilities).
- Loveland. Plan review is estimated at 20 to 30 working days per round (Loveland). A fire pit on a permanent gas line needs a building permit (LFRA). The city designs for a 30 psf ground snow load and 130 mph gusts (design criteria), which a solid patio cover has to carry.
- Berthoud. Permits cover patio covers, pergolas over 120 square feet or attached to the house, gas piping, fireplaces, electrical work and plumbing (Berthoud). The town’s guide notes pergolas typically aren’t designed for snow loads, and caps patio covers at 12 feet (Berthoud guide).
- Windsor. Ask the Permit Technician whether a pergola or patio cover needs a permit; structures must meet setbacks, and a new sprinkler system needs a permit on Town or non-potable water (Windsor FAQ). Electrical and plumbing contractors need a current State of Colorado license (Windsor).
- Timnath. It depends on the structure and the code the town has adopted; ask Timnath Planning and its building department before the pergola is drawn.
- Unincorporated Larimer County. Pergolas whose roof is at least 67% open, and decks no more than 30 inches above grade that don’t serve a required exit door, need no building permit, but setbacks still apply (Larimer County).
How deep do the footings go?
Below the frost line: 30 inches in Fort Collins and Loveland (Fort Collins, Loveland), and 30 inches for footings on unincorporated land in Larimer and Weld counties (Larimer County, Weld County). Berthoud’s guide says to go at least to the local frost depth and ask the building department for the number; in Windsor and Timnath, ask too.
Fort Collins inspects patio-cover footing holes open, before framing and wiring are covered. Dig and inspect on bare ground, then compact the turf base once around posts already set. On clay, which the Colorado Geological Survey calls Colorado’s most significant geologic hazard, a footing below frost depth keeps a post and the turf edge around it from moving.
How do the HOA or metro district and the town fit together?
The committee reviews the whole yard first; the town then permits the parts that need it.
- One submittal for the whole yard. Monte Cielo in Longmont wants one landscape plan showing turf, patios, built-in barbecues and pools (Monte Cielo guidelines). Separate packets mean separate reviews and conditions.
- Committee approval isn’t a permit. Harvest in Berthoud and Waters Edge in Fort Collins say so on their request forms, and Water Valley in Windsor sends a new deck to its office first, then to the Town for a building permit (Water Valley guidelines).
- The grading is often fixed. The Masters at Mariana Butte bars landscape elements that disturb a lot’s engineered grading or change its drainage swales. Highland Meadows’ recorded declaration bars grading changes from the Town-approved plans and asks owners to keep sprinkler piping within 5 feet of foundations to a minimum (Highland Meadows covenants). A sunken fire pit or raised terrace needs that approval first.
- District utilities stay reachable. Raindance Metropolitan District in Windsor wants each non-potable meter pit and curb stop kept clear of rock, decks and patios (Raindance Metropolitan District).
Colorado law bars an HOA from prohibiting artificial turf in the backyard of a detached single-family home, though it may still apply design and aesthetic guidelines (C.R.S. 38-33.3-106.5). The statute speaks to the turf, not the pergola, kitchen or fire feature beside it. Not legal advice. Send the committee the whole plan, turf and all, in one packet.
How do you keep later work from damaging finished turf?
When a trade has to come back after the turf:
- Pull, don’t trench. A spare sleeve lets an electrician pull a new circuit or landscape-light wire without cutting the lawn; lighting a green is in putting green lighting.
- Lay a path. Plywood or ground-protection mats from the gate to the work, and no tracked machines on the turf. Integriturf warns that heavy objects left on turf can mat its fibers early.
What should I ask the turf installer about the rest of the project?
- “What has to be finished before you start?” A good answer: grading, every gas, power and irrigation line, footings and hardscape, with inspections passed.
- “How will the turf meet the patio, the kitchen base and the fire pad?” A good answer names each edge detail.
- “Where do the sleeves go?” A good answer puts them on the drawing the HOA approved.
Recent job


Questions
Questions about where turf goes.
How long should I allow for HOA or metro-district review before work starts?
Plan on weeks. Windsor Highlands’ committee has 45 days to decide a complete request, and no decision in that time counts as a disapproval. The Masters at Mariana Butte suggests submitting plans at least 45 days before work begins. Send the whole yard in one packet so the clock runs once.
Who should draw the plan?
Someone who can put every room, line and grade on one scaled drawing that the committee, the town and each trade can work from. Some communities say who: Heron Lakes in Berthoud wants submittals prepared by an architect, landscape architect or qualified designer, with grading contours at 1-foot intervals.
Can a pergola or outdoor kitchen be added after the turf is in?
Yes, but the turf has to be cut back or lifted where the footings and trenches go, the base recompacted, and the turf relaid and reseamed. Spare conduit sleeves laid under the lawn now turn a later power or irrigation run into a pull instead of a trench.
Do HOAs review the lighting around a patio and turf?
Often, yes. Heron Lakes needs committee approval for exterior lighting, aimed at the ground and house with the source hidden. The Masters at Mariana Butte allows landscape lighting only with written approval, subdued and shielded, and bans uplighting. Lighting a putting green has its own guide.
Can the turf go in first and the patio later?
It can, but it is the costly order: the patio’s digging and base run into the turf edge, equipment crosses the lawn, and the edge has to be cut and fastened again. If the budget splits the project, build the hardscape and run the lines first, and leave the turf for the second phase.
Sources
Where this comes from.
Not legal advice. This page reflects its sources as they read on September 26, 2026. Rules, rates and programs change; each link goes to the public source it came from.
Show every source32
- City of Fort Collins, Building Permits page: Residential Permit Exemptions and Fast-Track Permits · checked Sep 26, 2026
- City of Fort Collins Building Services, Residential Pergola Guide (2024 IRC, revised March 30, 2026) · checked Sep 26, 2026
- City of Fort Collins Building Services, Residential Patio Cover Guide (2024 IRC, revised March 25, 2026) · checked Sep 26, 2026
- City of Fort Collins Building Services, Fire Pit Policy and Requirements (effective August 11, 2021) · checked Sep 26, 2026
- City of Fort Collins, Building Code page: Current Building Codes and Design Criteria · checked Sep 26, 2026
- Fort Collins Utilities, Drainage Information Required for Residential Permit Applications · checked Sep 26, 2026
- City of Loveland Building Division, Loveland Building Code Amendments: Design Criteria · checked Sep 26, 2026
- City of Loveland Building Division, Permitting FAQ's · checked Sep 26, 2026
- Town of Berthoud Building Department, Projects Requiring a Permit · checked Sep 26, 2026
- Town of Berthoud, 2024 IRC Patio Covers/Carports, Building Guides for Homeowners (SAFEbuilt, January 2026) · checked Sep 26, 2026
- Town of Windsor FAQ: permits for decks, porches, pergolas, patio covers and sprinkler systems · checked Sep 26, 2026
- Town of Windsor, Building Permits page · checked Sep 26, 2026
- Larimer County Community Development, Building Permit Requirements (updated 08/07/2026) · checked Sep 26, 2026
- Larimer County Community Development, Structural Design Information (2024 IRC/IBC) · checked Sep 25, 2026
- Weld County Building Department, Design Criteria and Adopted Building Codes · checked Sep 25, 2026
- Loveland Fire Rescue Authority, Recreational Fire and Portable Outdoor Fireplaces (PDF) · checked Sep 25, 2026
- Colorado 811, Private Underground Utility Information · checked Sep 25, 2026
- 2021 International Residential Code, Sec. R401.3 Drainage (as published for Colorado by UpCodes) · checked Sep 25, 2026
- Colorado Geological Survey, Expansive Soil & Rock · checked Sep 24, 2026
- Select Surfaces, Artificial Grass Installation Guide (PDF) · checked Sep 26, 2026
- Integriturf, Synthetic Turf Installation Guide (PDF) · checked Sep 26, 2026
- SB23-178 signed act: C.R.S. 38-33.3-106.5(1)(i.5) · checked Sep 24, 2026
- Deer Meadows Metropolitan District, The Masters at Mariana Butte Architectural and Design Guidelines (updated 6/27/2023) · checked Sep 26, 2026
- Declaration of Covenants for Highland Meadows Golf Course Subdivision (recorded 04/21/2004) · checked Sep 26, 2026
- Water Valley Master Association, Design Guidelines & Architectural Standards (Wayback Machine copy) · checked Sep 26, 2026
- Raindance Metropolitan District, Non-Potable Irrigation Water page · checked Sep 26, 2026
- Design Guidelines of Monte Cielo, Sec. 12.2 Landscaping Plan · checked Sep 26, 2026
- Harvest, Application for ACC Ancillary Modification · checked Sep 26, 2026
- Waters' Edge Metropolitan District No. 1, Design Review Request Form · checked Sep 26, 2026
- Windsor Highlands Metropolitan District Nos. 1–10, Architectural Guidelines (approved 12/4/2020) · checked Sep 26, 2026
- Berthoud-Heritage Metropolitan District, Heron Lakes Residential Improvement Rules and Regulations (amended June 1, 2026) · checked Sep 26, 2026
- NOAA NCEI U.S. Climate Normals 1991–2020, station Fort Collins (USC00053005) · checked Sep 24, 2026
Next step
Planning the whole backyard? Let’s walk it together.
Tell us about your yard and how to reach you, and we’ll set up a time to come out.
Book a yard walk
Five quick questions. Then we’ll reach out to set a time.
- 1Your project
- 2Your town
- 3Size
- 4HOA and timing
- 5Contact